THEC Letter of Notification Timeline
Action | Timeline |
APSU determines they would like a new program and begins work on the Letter of Notification (LON) |
|
LON Submitted to Academic Affairs for first review | September/October Planning year 1 |
Submit LON to THEC for initial approval | January: Planning Year 2 |
Receive Final approval from THEC for the LON | May: Planning Year 2 |
External Review | July/August: Planning Year 2 |
Response to External Review | September/October: Planning Year 2 |
Final approval from THEC to send to Board | October: Planning Year 2 |
Placed on THEC Meeting agenda | November: Planning Year 2 |
THEC Commission Approval | January: Implementation Year |
Implement Program | August 2025: Implementation Year |
* All new program should be implemented in the Fall term.